Full Condo Remodel in Fort Lauderdale: What Happens Before It Looks Pretty

Gutted condo room with new metal ceiling framing and protected floors

Everyone loves the after photos. But the part that decides how a remodel turns out happens weeks earlier, when the walls are open and the plans meet reality.

We’re in the middle of a full condo remodel in a beachfront building on A1A in Fort Lauderdale, just north of Hugh Taylor Birch State Park, right across the street from the ocean. The scope covers the kitchen, two bathrooms, new framing, new doors, and opening up the layout. Here’s what the job looks like right now, and what our partner Carlos says about the timeline.

She grew up in this building. Then she came back.

This homeowner already knew the building. Years ago, her family owned an apartment here. She sold it, moved to a house, and after four years she missed being close to the ocean. So she sold the house and bought another condo in the same building.

She already knew what she wanted. She had heard about the work we did in another apartment in this building, liked it, and called us. This job also came through a neighbor whose remodel we finished last year. In condo buildings, word travels fast.

Her goal: an open space. A wall used to close off the kitchen entrance. Now we’re building an island, a big living room, and a layout that flows from one room to the next.

Step 1: Protect the building, then demo

Before a single wall comes down, we cover everything. In a condo, you share hallways, elevators and walls with neighbors, so dust and debris can’t travel. Floors get covered and taped, and openings get sealed with plastic.

Then comes demolition. In this unit that meant the kitchen and both bathrooms, down to the studs.

Floors covered and taped before demolition in a Fort Lauderdale condo

Step 2: Remove the soffit, move the pipes overhead

Once the walls were open, the real layout showed up. A soffit (a boxed-in section built to hide pipes) had been built around the copper pipes and the washer and dryer. It covered the plumbing, but it also made the room feel tight.

So we took it out. We’re building a new ceiling and running the pipes on top of it. As Carlos puts it, “now the area looks much bigger.”

If your condo has a boxed-in section along the ceiling or around the laundry area, there may be pipes behind it. Moving them takes more work up front, but it can win back space that makes the whole room feel different.

Open walls with exposed plumbing during a condo remodel in Fort Lauderdale

Step 3: Framing, electrical and plumbing

With demo done, the rebuild starts. Next up on this job:

  1. Framing: new walls, the new ceiling, and openings for new doors
  2. Electrical
  3. Plumbing: including the lines moving overhead

This is also when the layout changes become real. The wall at the kitchen entrance is gone, and the island and open living room are taking shape.

Gutted condo room with new metal ceiling framing and protected floors
New ceiling framing in a beachfront Fort Lauderdale condo

How long does a full condo remodel take?

We asked Carlos on site. His answer for this job: 3 to 4 months, permits and everything included.

Permits are part of the timeline, not an extra step after it. Every job is different, so the best way to get a real number for your condo is an on-site estimate.

Thinking about remodeling your condo?

GC Pro Remodeling is a licensed and insured Certified General Contractor serving homes and condominiums across South Florida: kitchens, bathrooms, flooring and painting. Estimates are free, and hablamos español.

Call (954) 683-0208 or visit our showroom to see tile, cabinet and countertop options in person.

Get Your Dream Home Today

Call us today for a free in-home consultation. We’ll discuss your vision, provide a detailed estimate, and get your project started.